Delivery of first MV-75 for testing officially delayed amid funding setbacks: Army

WASHINGTON — The Army will not meet its initial goal of receiving the first MV-75 tiltrotor long-range assault helicopter for testing by the end of this year, according to the service’s acquisition shop.
“Delivery of the MV-75 for testing will not occur by the end of 2026. The program made deliberate efforts toward this goal while making measurable program progress,” a spokesperson from the Army Acquisition, Logistics and Technology (ASA(ALT)) office told Breaking Defense on Nov. 20.
“The Army remains on a path to complete development and testing in approximately half the time of comparable historical programs,” they added.
In January, then-Army Chief Gen. Randy George said the service expected to accept an airframe for testing by the end of 2026. But a subsequent funding shortfall disrupted communications between the Army and Bell — the program’s prime contractor — contributing to the missed delivery target.
The Army has not yet determined when it will receive the first aircraft for testing, the ASA(ALT) spokesperson said. The service is working with Bell, a subsidiary of Textron, “to develop an updated, resource-loaded integrated schedule and schedule risk analysis to establish achievable milestones at an affordable cost,” they added.
Bell was selected as the prime contractor for the MV-75 Cheyenne II tiltrotor in late 2022. Developed under the Army’s Future Long Range Assault Aircraft program, the Army has said the Cheyenne will fly “twice as fast” and “twice as far” as any of the service’s existing assault helos. It’s also set to gradually replace at least some of the service’s UH-60 Black Hawk fleet once fielded.
The missed delivery target follows a funding shortfall that emerged earlier this year after the Army spent nearly all of its available fiscal 2026 funding for the MV-75 by July, according to Textron’s latest quarterly filing. The company continued work on the program while reducing spending to manage the funding shortfall, the report stated.
In July, the Army requested to shift $350 million in funding to the MV-75 program to support the company’s work building and testing eight prototype tiltrotor aircraft. Congress approved that reprogramming request during the third quarter, as Breaking Defense previously reported.
About $300 million was committed to the program in contract changes, covering costs the company and its suppliers had already incurred, Textron CEO Lisa Atherton said in October during an earnings call with investors.
According to the ASA(ALT) spokesperson, Bell “chose to continue certain activities at its own risk without additional funding.” Both the company and the Army said communications between the two halted during the funding gap and did not resume until Sept. 28 when the service received the reprogrammed funding.
“Once funding was received, normal contract execution and communications resumed. The funding gap affected the planned schedule; the Army and Bell are now assessing those effects and updating the program schedule and risk analysis to establish realistic, affordable milestones and delivery dates,” the spokesperson said. “As we restart, the focus is on disciplined execution with a risk-informed path ahead that fits within the available budget.”
Separately, uncertainty surrounding the fiscal 2027 budget could further complicate the program’s timeline. The Army requested more than $2 billion for the MV-75 program in FY27, all of which under discretionary spending, but delays in approving that funding could push back the aircraft’s first low-rate initial production (LRIP) contract, as Breaking Defense previously reported.
“With the start of the fiscal year in a [continuing resolution], we’d expect a possible push in the timing of the LRIP award. Previously, we were thinking Q4 into Q1 of next year,” Chief Financial Officer David Rosenberg said during the October earnings call.
Though the program has faced delays, Army Undersecretary Michael Obadal told Breaking Defense in a statement that the service still considers the aircraft a “priority” and is committed to delivering the aircraft to soldiers as soon as possible.
“Getting the MV-75 into hands of Army aviators will be the culmination of one of the biggest Army acquisitions. The Cheyenne meets the endurance and close combat demands of large-scale combat operations,” he said. “It extends the distance over which commanders can deliver, reinforce, and reposition assault forces. It’s a priority for the joint force.”
The delay in the aircraft’s delivery for testing, along with the potential LRIP delay, follows uncertainty over the MV-75 program’s schedule. During a call with reporters in April, Maj. Gen. Clair Gill, then the Program Acquisition Executive for Maneuver Air, declined to commit to dates for the aircraft’s first flight or start of production.
“It’s going to happen when it’s going to happen. So we are moving as fast as we can,” Gill said at the time. “If I was king, and I had all the money in the world and all the engineers, and there were no limits, we probably would be able to do it in a matter of months.”